An Agile Retrospective on the Project That Broke Me (Part 2 of My 25-Year Look Back) Part 1 is here

I’ve carried this story in my head for years, sharing bits and pieces during trainings, almost like a form of group therapy. But now, I’m putting it all down in full detail with the hope that telling it will finally help exorcise this demon once and for all.

The Project That Had It All

At the peak of my consulting career, I was hired to manage a full system replacement project. It was exactly the kind of work I loved: high stakes, delivery focused, and with real autonomy. The rules were simple. Deliver the project on time and within budget. How we got there was up to me.

We built a blended team:

  • 3 vendor teams focused on platform development
  • 1 internal team on data migration
  • 1 internal team for legacy app integration

We used Scrum at the team level but didn’t buy into big scaling frameworks. Our scaling model was fit for purpose, something I jokingly called “The Dan Model.” It worked.

We weren’t doing continuous releases. This was a full system replacement, so we built to critical mass and planned quarterly internal releases for integration testing and UAT. Sprints were three weeks. We tracked scope, burnup, quality, and budget. And we were delivering.

What made this project special wasn’t just the numbers. It was the team.

When I arrived, IT was ranked 13th out of 13 departments in job satisfaction. The team was burnt out, distrustful, and beaten down.

I introduced daily scrums, and I don’t mean standups for show. I mean functional accountability every single day. People stepped up or opted out. A couple of lifers left early, which gave the rest of the team room to thrive.

I wasn’t a developer, unless you count Fortran and Pascal in college, but I had worked with development teams for 20 years. I knew how to ask the right questions, push through the noise, and translate technical issues into business risk, cost, and timing.

My approach was simple.

If you brought me a problem, bring me the options.

I would keep asking questions until we all understood the issue, usually after they dumbed it down enough for me, and then we would make the decision together.

Over time, we developed a level of trust that I had rarely experienced on a project. People spoke up. Problems surfaced early. Decisions got made. People wanted to be there.

A year later, we ran the culture survey again.

IT ranked #1 in job satisfaction.

That is still one of the things I’m most proud of in my career.

So when I accepted a full-time role to stay and lead the effort through delivery, I thought I had found my forever job.

I was wrong.

Then the Executive Interference Started

Halfway through the project, we had built enough functionality for our first external release. Our SMEs, now acting as product owners, ran full UAT and gave us the green light.

We were ready to release.

Then our executive sponsor, the CFO, retired.

Her replacement was a director from inside the organization who had been promoted into the role. She hadn’t been involved in the project. She hadn’t seen the progress, the process, or the results. But now she was in charge.

Whether it was fear, pressure to prove herself, or some performance incentive, I don’t know. One of her first major decisions was to bring in one of the Big 3 consulting firms to audit the project.

They audited us using standard PMI waterfall criteria.

Of course we failed.

  • No task-level project plans
  • No formal risk register
  • No stage gate documentation

We weren’t following waterfall. We weren’t supposed to be following waterfall. We were delivering working software.

At first, I actually laughed about it with my boss, the CIO.

“Of course we failed. We’re not doing any of that.”

But the new CFO was serious. My boss, who was a peacekeeper by nature, agreed that we needed to fix it.

The Collapse Begins

We hired a full-time project manager to build all the required artifacts.

Then we hired another one.

They still couldn’t keep up because the teams were moving faster than the documentation could be produced.

Now we were over budget.

The project was still delivering. The team was still strong. But we were spending more and more money making the project look right on paper.

I did everything I could to keep that noise away from the teams, but eventually it started getting through. Confidence dropped. People started questioning decisions that had made perfect sense only months earlier. The energy changed.

The CFO also refused to allow our first external release. She considered it too risky. Instead, she wanted the entire system completed and replaced in one big bang.

So we kept building.

And auditing.

And documenting.

Six months later, we had another formal audit.

Again, there was no meaningful discussion of working functionality, low defect rates, or scope control.

Just red marks against the required artifacts.

During that meeting, with only the auditor, the CEO, CIO, CFO, and me in the room, I felt my chest tighten. For the first time in my life, I started having heart palpitations. Then, embarrassingly, I felt tears welling up.

I glanced at my phone, made up an emergency production issue, and left the room.

Two weeks later, I resigned.

And Then It Fell Apart

After I left, the project continued and kept getting worse.

The budget tripled.

The system was never released.

Blame went everywhere. The vendor. The team. Probably me too.

By then, it didn’t really matter.

We had working software. We had a team that believed in the work. We had trust. We had results.

And we lost all of it, not because the project was failing, but because leadership didn’t trust the way it was succeeding.

Unfortunately, this wasn’t the only time I saw executive intervention damage a project. It happened more often than I care to admit.

This was simply the most egregious and the most painful.

Aftermath

Six months after leaving, I moved to Hawaii and spent the next five years delivering Agile training.

I shared this experience with thousands of people. I tried to help others avoid some of the mistakes I had seen and remind myself why I believed in Agile in the first place.

I also needed some distance from consulting.

It took five years before I felt ready to step back into a client environment again.

What’s the Advice?

After my last post, Al Shalloway asked what advice I would give others.

In this case, I’m still not sure.

We educated the executives early. We had their buy-in. We delivered results.

Maybe it was bad luck.

Maybe I missed a red flag.

Maybe there was something I could have done differently.

I do know there is a risk that comes with trying to change how organizations work. You aren’t just changing process. Sometimes you are challenging long-established habits, organizational politics, and people’s sense of control.

I know I’m not the only person who has run into that wall.

Some days, I wish I had taken the simpler path and changed code instead of people.

Thanks for letting me finally put this story out there. I’ve carried it around for almost a decade.

No regrets.